01-27-2016, 06:31 AM
(01-26-2016, 01:17 PM)jacketree link Wrote:Pick any two.
A 50,000 seat stadium completed within a year for $100 million was quite a feat. There are a number of reasons this was accomplished:
1. Some of the design was really clever. I know the geotechnical engineer who came up with the mechanically stabilized earth solution that allowed the new footprint to fit in the old stadium while meeting all building codes, particularly seismic, without costing a fortune.
2. No fault trace directly through the middle of the stadium helps hold costs down.
3. John Arrillaga wields a lot of power in the South Bay development, real estate, engineering and heavy construction industries. He called in a number of chits.
4. I recall the winter of '05-'06 as fairly mild. Otherwise forget it.
5. Some of the design and construction is just really cheap. The lead CM told a group of us that they initially thought the upper deck would actually be water tight based on what the sales people told them. Wrong. I recall the first lovely coke drips from above. This is a really lightweight structure. It will be interesting to see how it ages. Aluminum tends to due weird stuff as it oxides.
Stanford Stadium 2.0 is modeled after SMU's Gerald J. Ford Stadium.
Maybe it does start to show its age in 10 years. So what? A cost of $5M per year is peanuts. It'll probably be less than Shaw will be making by then.

![[Image: 384.jpg]](http://texasbob.com/stadium/simages/384.jpg)